Work gets under way on East End groins | RESTORE Dauphin Island
http://www.restoredauphinisland.com/...ns-300x225.jpgQuote:
Crews have been hard at work off the East End beach of Dauphin Island, where they’re utilizing barges, cranes and other heavy equipment to take apart and re-orient the rock groins. This photo was taken earlier this month (October). In early November, a deep-water dredge will begin pumping sand to elevate and widen the beach, using about 300,000 cubic yards of sand. Weeks Marine Inc. won the $6.7 million contract for the work, which officials said will take up to four months.